House Update
We stopped by the house yesterday and thought it might interest some on the progress of our future dwelling.
Concrete has been laid at each of the entrances, as well as the drive way and the stairs leading up to our front door. Siding on the back and east side of the house has been hung.
On the inside, the walls have been mudded, taped, and textured. Base boards and door frames are also in the process of being installed.
As of today, the final inspection is set for August 29th.